Note: This summary is not intended to be an all inclusive discussion of all state statutes on construction or mechanic’s lien laws, but does include basic provisions.This by no means constitutes a complete discussion of construction lien law and should not be interpreted as such. Parties seeking to know more about construction laws in their State should always consult their State statutes directly or an attorney.
State Statutes
ALABAMA DIRECT LIEN STATE
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 4 months from last furnishing
- Notice of Unpaid Balance must be served 5 days prior to actual Lien being filed Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 6 months from due date of last invoice Suit on Bond
- Within 1 year from Completion of project
ALASKA DIRECT LIEN STATE
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing or 15 days from Owners notice of Completion Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 6 months from date Lien was filed Suit on Bond
- Within 1 year from completion of project
ARIZONA DIRECT LIEN STATE
Preliminary Notice
- Within 20 days from first furnishing (Commercial)
- Within 20 days from first furnishing (Residential)
- Within 20 days from first furnishing (Public) Liens
- Within 60 days of Notice of Completion or 120 days from Completion of project Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 6 months from date Lien was filed Suit on Bond
- Within 1 year from final furnishing
ARKANSAS LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing
- Notice of Unpaid Balance must be served 75 days from last furnishing Lien
- Within 120 days from last furnishing
- Intent to Lien must be filed 10 days prior to Actual Lien being filed Bond Claim
- Within 90 days of last furnishing Foreclosure
- Within 15 months from date Lien was filed Suit on Bond
- Within 6 months from of last furnishing
CALIFORNIA DIRECT LIEN STATE
Preliminary Notice
- Within 20 days from first furnishing (Commercial)
- Within 20 days from first furnishing (Residential)
- Within 20 days from first furnishing (Public) Liens
- Within 90 days from Completion of Project or 30 days from Notice of Completion Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 6 months of last furnishing or 6 months from Completion of Project Suit on Bond
- Within 6 months from Completion of Project
COLORADO DIRECT LIEN STATE
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Lien
- Within 4 months from last furnishing
- Lien notice must be served 10 days prior to actual Lien Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 6 months from last month or 6 months from Completion of Project Suit on Bond
- Within 90 days from final settlement
CONNECTICUT LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing
- Notice of Intent to Lien must be served with lien Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 1 year from date Lien was filed Suit on Bond
- Within 1 year from last furnishing
DELAWARE LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing(Done by filing a Lawsuit) Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 90 days from last furnishing Suit on Bond
- Within 1 year from Completion of Project
DISTRICT OF COLUMBIA LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Lien
- Within 3 months from Completion of Project Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 1 year date Lien was filed or 6 months from Completion of Project Suit on Bond
- Within 1 year from final payment on Original Contract
FLORIDA LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Within 40 days from first furnishing (Commercial)
- Within 40 days from first furnishing (Residential)
- Within 40 days from first furnishing (Public) Liens
- Within 90 days from last furnishing Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 1 year from date Lien was filed Suit on Bond
- Within 1 year from last furnishing
GEORGIA LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Within 30 days from first furnishing (Commercial)
- Within 30 days from first furnishing (Residential)
- Within 30 days from first furnishing (Public) Liens
- Within 3 months from last furnishing Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 12 months from date debt became due Suit on Bond
- Within 1 year from Completion of Project
IDAHO DIRECT LIEN STATE
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 6 months from date Lien was filed Suit on Bond
- Within 6 months from Completion of Project
ILLINOIS LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Lien Notice within 90 days from last furnishing
- Lien within 4 months from last furnishing Bond Claim
- Within 90 days from last furnishing up to 180 days
- Lien on State funds 60 days from last furnshing Foreclosure
- Within 2 years from date of last furnishing Suit on Bond
- Within 6 months from Completion of Project Lien on Funds
- Within 90 days from date lien filed
INDIANA DIRECT LIEN STATE
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Within 30 days from first furnishing (Residential Existing)
- Within 60 days From first furnishing(New Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 60 days from last furnishing
- Within 90 days from last furnishing (Commercial) Bond Claim
- Within 60 days from last furnishing Foreclosure
- Within 1 year from date Lien was filed or 30 days from Notice to Commence Suit Suit on Bond
- Within 60 days of Completion of Project
IOWA LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Within 30 days from first furnishing (Commercial)
- Within 30 days from first furnishing (Residential)
- Within 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing Bond Claim
- Within 30 days from Completion of Project Foreclosure
- Within 2 years from last furnishing Suit on Bond
- Within 60 days from Completion of Project
KANSAS DIRECT LIEN STATE
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 3 months from last furnishing Bond Claim
- Within 90 days from last furnishing(Watch terms on Bond) Foreclosure
- Within 1 year from date Lien was filed Suit on Bond
- Within 6 months from Completion of Project
KENTUCKY LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Notice of Contract
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public)
- Protects from subsequent mortgages or conveyances
Notice of Intent to File a Lien
Residential Projects - Owner Occupied Single Or Double Family Dwelling within 75 days of Last furnishing
- Other Private Projects Projects under $1,000.00 within 75 days of last furnishing Projects over $1,000.00 within 120 days of last furnishingLiens
- Within 6 months from last furnishing, recommended 120 days from last furnishing Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 12 months from date Lien was filed Suit on Bond
- Within 6 months from date Claim is filed
LOUISIANA DIRECT LIEN STATE
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 30 days after filing an Acceptance by Owner or Within 60 days from Completion of Project if no Notice of Contract was filed Bond Claim
- Within 45 days from Completion of Project Foreclosure
- Within 1 year from date Lien was filed Suit on Bond
- Within 6 months from date Claim was filed
MAINE LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 120 days from last furnishing Suit on Bond
- Within 1 year from last furnishing
MARYLAND DIRECT LIEN STATE
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Intent to Lien within 90-120 days from last furnishing
- Lien to be served 180 days from last furnishing by filing suit Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 180 days from last furnishing Suit on Bond
- Within 1 year from last furnishing
MASSACHUSETTS LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Within 30 days from first furnishing Notice of ID(Commercial)
- Within 30 days from first furnishing Notice of ID(Residential)
- Within 30 days from first furnishing (Public) Liens
- Notice of Contract within 60 days of Notice of Completion
- Statement of Account within 90 days of Notice of Completion Bond Claim
- Within 65 days from last furnishing Foreclosure
- Within 90 days from date Lien was filed Suit on Bond
- Within 1 year from last furnishing
MICHIGAN LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Within 20 days from first furnishing (Commercial)
- Within 20 days from first furnishing (Residential)
- Within 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 1 year from date Lien was filed Suit on Bond
- Within 1 year from Completion of Project
MINNESOTA LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Within 45 days from first furnishing (Commercial)
- Within 45 days from first furnishing (Residential)
- Within 30 days from first furnishing (Public) Liens
- Within 120 days from last furnishing
- Lien notice must be served 10 days prior to actual Lien Bond Claim
- Within 120days from last furnishing Foreclosure
- Within 1 year from last furnishing Suit on Bond
- Within 1 year from last furnishing
MISSISSIPPI LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing
- Stop Notice for supplier/subcontractor direct to GC Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 12 months from date debt became due Suit on Bond
- Within 1 year from Completion of Project
MISSOURI DIRECT LIEN STATE
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Lien
- Within 6 months from last furnishing
- Lien notice must be served 10 days prior to actual Lien Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 6 months from date Lien was filed Suit on Bond
- Within 90 days from Completion of Project
MONTANA DIRECT LIEN STATE
Preliminary Notice
- Within 30 days from first furnishing (Commercial)
- Within 20 days from first furnishing (Residential)
- Within 60 days from first furnishing (Public)Liens
- Within 90 days from last furnishing or 60 days from Notice of CompletionBond Claim
- Within 90 days from Acceptance of JobForeclosure
- Within 2 years from date Lien was filedSuit on Bond
- Within 1 year from last furnishing
NEBRASKA LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Lien
- Within 120 days from last furnishing Bond Claim
- Within 90-4 months days from last furnishing Foreclosure
- Within 2 years from date Lien was filed Suit on Bond
- Within 1 year from final settlement Principal Contract
NEVADA DIRECT LIEN STATE
Preliminary Notice
- Within 31 days from first furnishing (Commercial)
- Within 31 days from first furnishing (Residential)
- Within 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing or 40 days from Notice of Completion Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 6 months from date Lien was filed Suit on Bond
- Within 1 year from last furnishing
NEW HAMPSHIRE DIRECT LIEN STATE
Preliminary Notice
- Before first furnishing Provide a Notice of Account every 30 days (Commercial)
- Before first furnishing Provide a Notice of Account every 30 days(Residential)
- Within 30 days from first furnishing (Public) Liens
- Within 120 days from last furnishing by filing lawsuit Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 120 days from last furnishing Suit on Bond
- Within 1 year from date of Claim
NEW JERSEY LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing
- Notice of Unpaid Balance must be served 10 days prior to actual Lien Bond Claim
- Within 60 days from Completion of Project is recorded
- 90 days from last furnishing
- Lien on Funds may be available Foreclosure
- Within 1 year from date Lien was filed Suit on Bond
- Within 1 year from last furnishing
NEW MEXICO DIRECT LIEN STATE
Preliminary Notice
- Within 60 days from first furnishing (Commercial)
- Within 30 days from first furnishing (Residential)
- Within 60 days from first furnishing (Public) Liens
- Within 60 days from Completion of Project Bond Claim
- Within 90 days from last furnishing Foreclosure
- Within 2 years from date Lien was filed Suit on Bond
- Within 1 year from Completion of Project
NEW YORK LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Not required but recommended 30 days from first furnishing (Residential)
- Not required but recommended 30 days from first furnishing (Public) Liens
- Within 90 days from last furnishing, Up to 8 months if you know payment has not been made
- Public Improvement Lien within 30 days of Completion Bond Claim
- Within 90-120 days from last furnishing Foreclosure
- Within 1 year from last furnishing
- Within 6 months of PI Lien Suit on Bond
- Within 1 year from last furnishing
NORTH CAROLINA LIMITED TO UNPAID PORTION OF THE GENERAL CONTRACT
Preliminary Notice
- Not required but recommended 30 days from first furnishing (Commercial)
- Required if Notice of Contract is filed by General Contractor (Full Lien Rights)
- Not required but recommended 30 days from first furnishing (Residential)
- Required if Notice of Contract is filed by General Contractor (Full Lien Rights)